black and white bed linen

Commercial builders for the places WA eats, learns, shops, works and refuels.

Paradox Build & Design delivers new builds, fit-outs and refurbishments for QSR, childcare, retail, large format retail, industrial and fuel clients across Perth and regional Western Australia.

85+

5

core sectors: QSR, childcare, retail, LFR, fuel

$20M

P&I insurance cover

years combined construction experience

What we build

We work in five sectors and know their fit-out standards, approvals and operating pressures. Most of our work is design and construct, so one team carries a project from concept to handover.

New early learning centres, from site works and slab to steel frame, fit-out and outdoor play areas.

QSR

Childcare

Retail

Quick-service restaurant fit-outs, refurbishments and equipment upgrades, including works staged inside trading stores.

Tenancy fit-outs, shopfronts and refurbishments in centres and standalone sites, delivered to the landlord's and the brand's requirements.

LFR

Large format retail, warehousing and industrial: bulky goods showrooms, warehouses and industrial units, from slab and structure through to office and showroom fit-out.

FUEL

Food court and tenancy fit-outs within highway service centres.

New Builds

Ground-up commercial buildings, including earthworks, slab, structure and services.

Fit-Outs

Base building to opening day, turnkey to operational trade.

Refurbishments

Upgrades to existing sites, programmed to keep closures as short as possible.

Design & Construct

Design, approvals and construction under one contract, with value engineering from the start.

Projects

We apply sound construction methodology and value engineering to deliver quality projects quickly while protecting our clients' budgets. Here is what's on site now and recently delivered.

Gowrie Early Learnin

Architect's render, then progress from earthworks to frame. Tap a photo to enlarge.

McKail

Contract
Design & Construct

Site Area
3,302 m²

Gross floor area
552 m²

Places
92

Car park
1.500 m²

Construction time
25 weeks

A new early learning centre for 92 children, delivered design and construct. The steel frame and roof structure are up and the build is moving into enclosure.

Under construction

Research and Development Centre

Site camera time-lapse, excavation to frame (daylight frames only).

Bentley

Contract
Design & Construct

Site Area
1,140 m²

Gross floor area
410 m²

Places
51

Car park
390 m²

Construction time
24 weeks

A design and construct build on a tight 1,140 m² site, with the steel frame raised over the slab while the neighbouring car park stays in use.

Under construction

KFC Kwench roll-out

Architect's render, then progress from earthworks to frame. Tap a photo to enlarge.

Perth metro and regional WA

Client
KFC

Stores Surveyed
38

Metro / Regional
30 / 8

Scope
Survey, design input, permits, demolition, construction

Time on site
About 3 days per store, while trading

KFC engaged us to survey 38 stores and help design the installation of the new Kwench drink line. We then handle permits, demolition and construction inside operating restaurants, with about three days of works per store.

National roll-out

KFC food court fit-outs

BORR service centres, Waterloo

Contract
Turnkey fit-out to operational trade

Gross floor area
160 m²

Construction time
6 weeks

Two inline KFC tenancies in the north and southbound service centres on the Bunbury Outer Ring Road.

Residential redevelopment

North Perth Development

Balga

North Perth

Two three-bedroom, two-bathroom villas and a four-bedroom, three-bathroom townhouse, each with a double garage.

A multi-level building with curved balconies and timber screening.

Contract
Design and Construct

Construction time
26 weeks

Site Area
728 m²

Stage
Design

How we work

Our clients are operators: franchise groups, early learning providers and developers who need a site open on a date. We plan every job around that date.

Value engineering from day one

Because we usually design and construct, we can test materials, structure and services against the budget before drawings are locked, rather than cutting scope later.

Built around trading hours

Much of our QSR work happens inside open restaurants. We stage demolition and construction so stores keep serving, and the Kwench works take about three days per store.

Handover means open for trade

Our fit-outs finish turnkey, with equipment installed, services commissioned and the site ready for staff to start trading.